Kingman Picks One Drainage Basin to Finish Flying Fortress Parkway

Kingman City Council voted at a 5 p.m. special meeting on Tuesday, Oct. 27, 2026, to build one large stormwater basin on donated land near Interstate 40, instead of 15 smaller basins along Flying Fortress Parkway.

The vote covers the third phase of the parkway, the remaining stretch of road toward the airport. That parkway ties into the Flying Fortress interchange, which the city opened on Oct. 5, 2026, at I-40 Exit 56. A separate interchange job on the west side of town is still under construction, as described in West Kingman I-40/US 93 Interchange Hits 80% as Beale Street Tunnel Opens.

The council approved what staff called Option B on a voice vote, with no opposition stated on the city’s meeting recording. The motion, made by Councilman Smiley W., also directed staff to bring the land dedication back to the council for acceptance.

What are the two options?

City Manager Tim W. and City Engineer Mike G. told the council the city already has 95% design plans for Phase 3. Those plans, known as Option A, would put 15 cascading detention basins about 10 feet deep in the parkway right of way, covering about 6.8 acres.

Option B would put one basin on donated land close to I-40, upstream of the parkway. Mike G. described it as a conceptual design about 20 to 25 feet deep and about five acres in size, dug deep enough that the city can use the dirt to build Phase 3 instead of bringing in fill.

Why change the plans this late?

Staff said the new road will change how water moves in a 100-year storm. Mike G. said the parkway itself adds about 300 cubic feet of water per second, and either option is meant to take that amount back out so downstream flows stay at pre-existing conditions.

Tim W. said the property owner had asked the city for help getting access from the Arizona Department of Transportation, and staff had stayed with Option A because the city could not guarantee that access. Just before the Oct. 20 regular meeting, he said, the owner agreed to donate the land without that condition. Council members continued the item that night because they did not have enough cost and schedule information.

Mike G. also said the 15 basins along the road would likely be temporary. If a later project farther upstream cut storm flows to a 10-year level, those basins would no longer be needed.

What does the change cost?

Mike G. said the Option A basins would cost about $6 million, plus a little more than $1 million to borrow, haul, and place about 39,000 cubic yards of extra fill. The conceptual Option B basin would cost a little less than $6 million and would supply the dirt for the road.

Even with an added redesign cost of about $330,000, he and council members described Option B as cheaper by roughly $1 million or more. The $330,000 is a proposal from the design firm AECOM to redraw the plans, with a commitment to finish 100% plans by Dec. 14, 2026.

Councilwoman Jamie S. asked whether the new numbers still fit the project’s budget. Tim W. said they do, and that the design change would be covered by funds already budgeted for the project.

When will the work get done?

AECOM’s Dec. 14 date is for finished design plans, not for construction. If the plans are done on time, Tim W. said a bid closing in mid to late January would make sense because of the holidays.

Vice Mayor Cherish S. said the redesign would put the project about two months behind. Tim W. said Option B adds that redesign time, but he did not expect the construction period itself to change much once the job is out to bid. He also said the chosen design meets the flow rules for the road all the way to the airport.

What will the basin do?

Both options are designed to handle the city’s own impact in a 100-year storm, Mike G. said. The Option B basin would pull only the top of the flow off Rattlesnake Wash and would not reduce flooding downstream.

The donated parcel is in a floodplain, so the city will need a floodplain fill permit from Mohave County. Mike G. said FEMA paperwork could wait until after the work is done.

Staff also said Option B would not block a later, larger basin farther north. They said the FAA would not be involved if no work is done on city land under FAA control, and that the state transportation department is no longer in play because the landowner dropped the access request.